Chapter 2: Commissioning procedures 5
Chapter 2: Commissioning procedures
This chapter will guide you through the commissioning process for an SmartPilot X
system. It includes:
Initial setup.
Dockside calibration.
Seatrial calibration.
The ST70 Autopilot Controller has an initial setup and calibration wizard, which will
take you through the commissioning process. Your autopilot will select the setup
screens relevant to your system. Those that are not relevant will be skipped
automatically.
Note: If you already have an ST70 instrument installed, some settings will be automatically
transferred from that and the wizard will skip those settings.
2.1 Switching on and initial setup
With the boat safely tied up, use these initial setup instructions to switch on the
autopilot system and controller, and to carry out the following initial setup procedures:
Select language.
Set boat type.
Set date and time format (only if GPS is fitted).
Set correct local time (only if GPS is not fitted).
Set required data units.
Note: In order to carry out calibration procedures you must complete initial setup.
If the system has previously been set up and calibrated this part of the setup wizard
will not be displayed and you can continue immediately with dockside calibration.
WARNING: Calibration requirement
All autopilot systems must be calibrated before use.